FAT and SAT Explained: Factory and Site Acceptance Testing for GMP Equipment

What factory and site acceptance tests check, how they differ, what documents you need, and when Annex 15 lets FAT and SAT results count towards IQ and OQ.

Cybroscape Technologies8 min read

Key takeaway

What factory and site acceptance tests check, how they differ, what documents you need, and when Annex 15 lets FAT and SAT results count towards IQ and OQ.

FAT and SAT are the two acceptance tests for new equipment. The factory acceptance test (FAT) happens at the supplier's site before the equipment ships. The site acceptance test (SAT) happens at your site after it is installed. FAT asks whether the supplier built what you ordered. SAT asks whether it still works once it is in your building, connected to your utilities.

Both sit between design qualification and IQ in the qualification lifecycle. Done well, they find problems while they are cheap to fix, and their results can count towards IQ and OQ so you do not test the same thing twice.

FAT vs SAT at a glance

FATSAT
WhereSupplier's factoryYour site, after installation
WhenBefore shippingAfter delivery and installation, before or alongside IQ
Main questionWas it built to the specification?Does it work in our environment?
UtilitiesSupplier's, often simulatedYours: power, water, air, network
Who writes the protocolUsually the supplier, approved by youYou or the supplier, approved by you
OutcomeApproval to ship, plus a punch listApproval to start qualification

What a factory acceptance test checks

FAT checks the equipment against your user requirements and the agreed functional specification before it leaves the factory. Fixing a fault there costs a fraction of fixing it after shipping.

  • Construction: materials of construction, welds, surface finish and dimensions against drawings.
  • Documentation: drawings, wiring diagrams, material certificates, manuals and the software version.
  • Function: each operating sequence, at normal settings and at the limits.
  • Alarms and interlocks: each one triggered and confirmed, including emergency stop.
  • Control software: user levels, recipes, audit trail and data storage for automated equipment.
  • Safety: guards, labels and electrical checks.

Every failed check goes on a punch list with an owner and a date. Agree before the FAT which items must be closed before shipping and which can be closed on site.

What a site acceptance test checks

SAT repeats the checks that transport or installation could have changed, then adds the ones that need your site. Shipping can loosen connections, damage sensors or shift calibration, so the SAT confirms the equipment arrived in the condition it left.

  • Physical condition after shipping, and that all parts on the packing list arrived.
  • Connection to your utilities, and that they meet the equipment's needs.
  • Integration with your systems, such as the building management system, SCADA, MES or data historian.
  • Key functions and alarms re-run on site, with a focus on anything affected by the move.
  • Closure of the open punch list items from FAT.

Can FAT and SAT results count towards IQ and OQ?

Yes, if you plan for it. EU GMP Annex 15 allows tests done at FAT or other stages to count towards qualification, without repeating them on site at IQ or OQ. The condition is that you can show transport and installation did not affect the function tested.

In practice that means four things. The FAT or SAT protocol was approved in advance. It was run under good documentation practice, with signed and dated results. Your quality unit reviewed the results. And the qualification plan says which FAT and SAT tests are being used and why. ISPE's commissioning and qualification guide and ASTM E2500 take the same risk-based view.

Reusing good evidence is the biggest time saving in equipment qualification. Our post on using commissioning evidence in qualification covers the conditions in more detail.

Documents you need for FAT and SAT

  • User requirements specification and functional specification, to test against.
  • An approved FAT protocol and an approved SAT protocol with acceptance criteria.
  • A traceability matrix linking requirements to each test.
  • Completed test records, signed and dated by the people who ran and witnessed them.
  • The punch list, with each item closed or carried forward.
  • A FAT report and a SAT report, each with a clear pass or fail decision.

Running a remote FAT

Remote FATs became common when travel stopped in 2020 and many teams kept them. The supplier runs the tests on camera while your team watches, asks for checks and records results.

They work if you prepare more than for an in-person visit. Send the protocol early, agree camera positions for each test, and ask for close-ups of displays, labels and readings. Record the session, and have the supplier sign the results the same day. Keep anything that needs touch or close inspection, such as welds and surface finish, for SAT or a short site visit.

Common FAT and SAT mistakes

  • Testing against the supplier's standard checklist instead of your requirements.
  • No approved protocol, so results cannot count towards qualification later.
  • Signing the FAT off with open punch list items and no agreed plan to close them.
  • Repeating every FAT test at SAT and again at OQ, because nobody planned what could be reused.
  • Skipping the control software at FAT, then finding audit trail or user access gaps during OQ.

Where FAT and SAT fit in the qualification lifecycle

The usual order is URS, design qualification, FAT, SAT, then IQ, OQ and PQ. For what each of those qualification stages proves, see IQ, OQ, PQ and PPQ explained. For the wider picture of commissioning, qualification and validation, read our CQV guide.

Cybroscape GxP Copilot drafts the URS, risk assessment and test protocols for new equipment, and keeps the traceability matrix current as FAT, SAT and IQ/OQ/PQ results come in. Qualified people review and sign everything. See equipment qualification software for how it works.

Where to go next

Explore Cybroscape GxP Copilot for AI-native validation, Cybroscape TraceDraft for source-traceable clinical documentation, or book a demo to see either on your own data.

Part of our guide to GxP software: categories, evaluation criteria and how the platforms compare.

  1. 1URSWhat the equipment must do
  2. 2DQThe design meets the URS
  3. 3FAT / SATCommissioning evidence, reused
  4. 4IQInstalled as specified
  5. 5OQOperates across its ranges
  6. 6PQPerforms in routine use
Requalification when a change, deviation or periodic review calls for it
Equipment qualification under EU GMP Annex 15: each stage proves something the previous one cannot, commissioning evidence can be reused instead of repeated, and a defined change or event triggers requalification.
See it on your own systemBring a URS or a system. We run GxP Copilot against it live on the call.

Sources

Primary documents referred to on this page, from their official publishers.

fat satfat and satfactory acceptance testsite acceptance testfat vs satfat sat pharma
FAQ

Frequently Asked Questions

Prefer to talk first? Chat with us on WhatsApp or book a call with an expert.

Talk to an expert
What is the difference between FAT and SAT?

FAT, the factory acceptance test, is done at the supplier's site before shipping to check the equipment was built to specification. SAT, the site acceptance test, is done at your site after installation to check it works with your utilities and systems.

Is FAT and SAT required by GMP?

EU GMP Annex 15 lists FAT and SAT as qualification stages to use where appropriate. For complex or new equipment they are expected good practice. Simple items may need only a check at delivery and IQ.

Can FAT results replace IQ or OQ tests?

Partly. Annex 15 allows tests done at FAT to count towards qualification if you can show transport and installation did not affect the function, the protocol was approved in advance and QA reviewed the results.

Who attends a FAT?

Usually the supplier's test engineers, your project or engineering lead, a validation or CQV engineer and, for critical equipment, someone from quality. End users often join to check usability.

Keep reading

All articles
ValidationPharmaceutical Water System Qualification: Commissioning and Qualification Steps for PW and WFIStep-by-step commissioning and qualification of purified water and WFI systems: IQ, OQ, the three-phase PQ, sampling, limits and common inspection findings. · 10 min readValidationValidating a Data Migration: Moving GxP Records Without Losing ThemReplacing a validated system means moving its records. What regulators expect from a migration, how to prove nothing was lost or altered, what to do with data you cannot migrate, and the checks that catch silent corruption. · 6 min readValidationDecommissioning a GxP System: Retiring It Without Losing the RecordsSwitching a validated system off is a controlled activity, not an IT task. What has to happen before shutdown, how to keep records retrievable for their full retention period, and why half-retired systems are an inspection risk. · 5 min readValidationIQ, OQ, PQ and PPQ Explained: What Each Qualification Stage ProvesWhat IQ, OQ and PQ mean, what each stage checks, how PPQ fits into process validation, and what inspectors look for, with equipment and software examples. · 11 min readValidationThe Live Requirement Traceability Matrix: why derived beats maintainedStatic RTMs go stale by lunch. A live RTM derived on read is a different tool entirely. · 5 min readValidationProcess Validation in Pharma: FDA's Three-Stage Lifecycle Approach ExplainedA practical guide to process validation under FDA's 2011 guidance (Stage 1 design, Stage 2 qualification, Stage 3 continued verification) with real examples and common mistakes. · 6 min readValidationKeeping a SaaS system validated when the vendor releases on its own scheduleSaaS systems stay validated through a release routine: screen release notes, assess risk to GxP functions you use, test what matters in a preview environment, and record the decision. Most releases need only the assessment. · 3 min readValidationSpreadsheet validation in GxP: inventory first, template secondSpreadsheets that support GxP decisions need validation proportionate to what they do: template control for simple forms, verified and locked formulas for calculations, and software-level care, or replacement, for anything with macros. · 3 min read

Bring a system. We'll show you the package.

Book a demo, or ask a validation lead a quick question on WhatsApp.

  • We reply within one business day
  • We run your URS live on the call
  • You get a clear plan for your system

Book a demo

Four fields. The right specialist replies within one business day.

Your details stay private. We never share them.