FAT and SAT are the two acceptance tests for new equipment. The factory acceptance test (FAT) happens at the supplier's site before the equipment ships. The site acceptance test (SAT) happens at your site after it is installed. FAT asks whether the supplier built what you ordered. SAT asks whether it still works once it is in your building, connected to your utilities.
Both sit between design qualification and IQ in the qualification lifecycle. Done well, they find problems while they are cheap to fix, and their results can count towards IQ and OQ so you do not test the same thing twice.
FAT vs SAT at a glance
| FAT | SAT | |
|---|---|---|
| Where | Supplier's factory | Your site, after installation |
| When | Before shipping | After delivery and installation, before or alongside IQ |
| Main question | Was it built to the specification? | Does it work in our environment? |
| Utilities | Supplier's, often simulated | Yours: power, water, air, network |
| Who writes the protocol | Usually the supplier, approved by you | You or the supplier, approved by you |
| Outcome | Approval to ship, plus a punch list | Approval to start qualification |
What a factory acceptance test checks
FAT checks the equipment against your user requirements and the agreed functional specification before it leaves the factory. Fixing a fault there costs a fraction of fixing it after shipping.
- Construction: materials of construction, welds, surface finish and dimensions against drawings.
- Documentation: drawings, wiring diagrams, material certificates, manuals and the software version.
- Function: each operating sequence, at normal settings and at the limits.
- Alarms and interlocks: each one triggered and confirmed, including emergency stop.
- Control software: user levels, recipes, audit trail and data storage for automated equipment.
- Safety: guards, labels and electrical checks.
Every failed check goes on a punch list with an owner and a date. Agree before the FAT which items must be closed before shipping and which can be closed on site.
What a site acceptance test checks
SAT repeats the checks that transport or installation could have changed, then adds the ones that need your site. Shipping can loosen connections, damage sensors or shift calibration, so the SAT confirms the equipment arrived in the condition it left.
- Physical condition after shipping, and that all parts on the packing list arrived.
- Connection to your utilities, and that they meet the equipment's needs.
- Integration with your systems, such as the building management system, SCADA, MES or data historian.
- Key functions and alarms re-run on site, with a focus on anything affected by the move.
- Closure of the open punch list items from FAT.
Can FAT and SAT results count towards IQ and OQ?
Yes, if you plan for it. EU GMP Annex 15 allows tests done at FAT or other stages to count towards qualification, without repeating them on site at IQ or OQ. The condition is that you can show transport and installation did not affect the function tested.
In practice that means four things. The FAT or SAT protocol was approved in advance. It was run under good documentation practice, with signed and dated results. Your quality unit reviewed the results. And the qualification plan says which FAT and SAT tests are being used and why. ISPE's commissioning and qualification guide and ASTM E2500 take the same risk-based view.
Reusing good evidence is the biggest time saving in equipment qualification. Our post on using commissioning evidence in qualification covers the conditions in more detail.
Documents you need for FAT and SAT
- User requirements specification and functional specification, to test against.
- An approved FAT protocol and an approved SAT protocol with acceptance criteria.
- A traceability matrix linking requirements to each test.
- Completed test records, signed and dated by the people who ran and witnessed them.
- The punch list, with each item closed or carried forward.
- A FAT report and a SAT report, each with a clear pass or fail decision.
Running a remote FAT
Remote FATs became common when travel stopped in 2020 and many teams kept them. The supplier runs the tests on camera while your team watches, asks for checks and records results.
They work if you prepare more than for an in-person visit. Send the protocol early, agree camera positions for each test, and ask for close-ups of displays, labels and readings. Record the session, and have the supplier sign the results the same day. Keep anything that needs touch or close inspection, such as welds and surface finish, for SAT or a short site visit.
Common FAT and SAT mistakes
- Testing against the supplier's standard checklist instead of your requirements.
- No approved protocol, so results cannot count towards qualification later.
- Signing the FAT off with open punch list items and no agreed plan to close them.
- Repeating every FAT test at SAT and again at OQ, because nobody planned what could be reused.
- Skipping the control software at FAT, then finding audit trail or user access gaps during OQ.
Where FAT and SAT fit in the qualification lifecycle
The usual order is URS, design qualification, FAT, SAT, then IQ, OQ and PQ. For what each of those qualification stages proves, see IQ, OQ, PQ and PPQ explained. For the wider picture of commissioning, qualification and validation, read our CQV guide.